Chittering Road Bridges 4026 & 4027 - Reconstruction - 2020/21


Project Update - August 2020

The design stage of this project is currently underway. Our Technical Services Team is currently liaising with the required contractors to undergo site investigations and design works to enable this project to run smoothly. 

A traffic management plan is being developed to best manage the road closure. Sufficient public notice will be given prior to the commencement of onsite works and road closures. Whilst we understand the road closure will be inconvenient, there is no safe alternative to undertake these necessary works. 


Project Overview

There are two bridge in close proximity to each other on Chittering Road, south of Julimar Road. They are bridge number 4026 and 4027. Both of these bridges have been deemed to be at the end of their life and due for replacement. 

These works will involve the removal of the existing bridges and replacement with two 900mm culverts at each location. 

This project has been 100% funded by Main Roads Western Australia as the existing bridges are at the end of its life. 

These works will involve the closure of this section of Chittering Road for the duration of the onsite works. Traffic management will be in place and sufficient notice will be given prior to commencement.