Archibald Street - Road Reconstruction - 2020/21


Project Update - January 2021

Works on this project commenced in January 2021.

These works will be undertaken in conjunction with other road works within the Shire. Our team may come and go from site over the next few weeks as we work between our different projects. Traffic management will be in place for the duration of these works, please obey warning signage and take care when traveling in the area.

We anticipate these works to be completed in early April 2021.


Project Overview

These works will continue on from the reconstruction works undertaken in 2019/20.

The project will take place from SLK 1.03 - 1.46.

The current road surface is uneven and required renewal of the pavement and wearing surfaces. Renewal of the road surface will be undertaken by 200mm wet mixing of pavement and laying of 30mm asphalt seal.

These works have been partly funded by Council ($63,079) and Roads to Recovery Funding ($99,609). 

The Roads to Recovery program supports the maintenance of the nation's local road infrastructure assets, which facilitates greater access for Australians and improves safety and economic and social outcomes. This is a federally funded project and is 100% funded by the Federal Government.